Item no. Agenda Item Details Status
01 Apologies for Absence

No apologies for absence have been received.

02 Declarations of Interest

Members are reminded that they should declare any personal and/or prejudicial interests at this point and that they should leave the meeting room before any item, in which they have a prejudicial interest, is discussed.

03 Minutes

Members are asked to agree the minutes, attached marked 3, of the Audit and Performance Management Committee meeting, held on 24 November 2011, and that they be signed by the Chair as a correct record.

AttachmentSize
PDF icon 03-a-and-pm-minutes-24-november-2011.pdf43.12 KB
For decision
04 Public Questions

Members are asked to receive any questions, statements or petitions, of which notice has been received, from members of the public.

05 Audit and Performance Management Committee Proposed Work Plan 2012/2013

This report, attached marked 5, puts forward a 2012/2013 Work Plan for the Audit and Performance Management Committee for consideration and approval by Members.

AttachmentSize
PDF icon 05-a-and-pm-proposed-work-plan-2012-13.pdf249 KB
For decision
06 Audit Commission Matters
06a External Audit Statement of Audit Progress 2011/12

This paper, attached marked 6a, reports on the Audit Commission's progress in delivering its responsibilities as the Authority's external auditor. It also seeks to highlight key emerging national issues and developements, which may be of interest to Members. At the end of this update Members may wish to consider a number of questions in order to ensure that they have received sufficient assurance on the emerging issues.

AttachmentSize
PDF icon 06a-external-audit-statement-of-audit-progress-2011-12.pdf381.13 KB
06b Audit Plan 2011/12

This paper, attached marked 6b, sets out the work for the 2011/12 audit, which the Audit Commission proposes to undertake to support its opinion on the Fire Authority's 2011/12 financial statements and the value for money conclusion. The paper also advises of the Audit Commission's fee for 2011/12.

AttachmentSize
PDF icon 06b-audit-plan-2011-12.pdf706.92 KB
For information
07 Government's Response to the Future of Local Public Audit

This report, attached marked 7, provides Members with an update on the Government's response to the consultation on the Future of Local Public Audit, published in January 2012.

AttachmentSize
PDF icon 07 - Government response to future of Local Public Audit.pdf33.68 KB
For information
08 Internal Audit Programme 2012/13 to 2015/16

This report, attached marked 8, sets out a four-year programme of audit work for the period 2012/13 to 2015/16 and recommends that the Fire Authority approve the programme of audits for 2012/13, as set out in the appendix to the report.

AttachmentSize
PDF icon 08-internal-audit-programme-2012-13-to-2015-16.pdf80.59 KB
For decision
09 Information and Communications Technology Systems Failure and Internal Audit

This report, attached marked 9, summarises the issues identified following the internal audit of the failure of information and communications technology systems and identifies actions to rectify the situation.

AttachmentSize
PDF icon 09-ict-systems-failure-and-internal-audit.pdf66.93 KB
For information
10 Risk Management Group Internal Audit Progress Monitoring Report

This report, attached marked 10, provides Members with an update on the monitoring of recommendations made by Internal Audit, which is undertaken by the Risk Management Group. It specificially covers details about the progress made against outstanding recommendations.

AttachmentSize
PDF icon 10-rmg-internal-audit-progress-monitoring-report.pdf34.78 KB
For information
11 Annual Governance Statement
11a Timetable

This report, attached marked 11a, informs Members of the process, which will be put in place to ensure that the Fire Authority's Annual Governance Statement is ready for inclusion in the Final Accounts for 2011/12.

AttachmentSize
PDF icon 11a-annual-governance-statement-timetable.pdf26.51 KB
For decision
11b Improvement Plan 2011/12

This report, attached marked 11b, summarises the progress made to date against the improvements contained in the Annual Governance Statement Improvement Plan 2011/12.

AttachmentSize
PDF icon 11b-ags-improvement-plan-2011-12.pdf32.37 KB
For information
12 Review of Anti-Fraud and Corruption Strategy

This report, attached marked 12, requests the Committee to recommend that the Fire Authority re-affirm the Anti-Fraud and Corruption Strategy, following the annual review conducted by officers.

AttachmentSize
PDF icon 12-review-of-anti-fraud-and-corruption-strategy.pdf181.49 KB
For decision
13 Review of Whistleblowing Policy

This report, attached marked 13, requests the Committee to recommend that the Fire Authority re-affirm the Whistleblowing Policy, following the annual review conducted by officers.

AttachmentSize
PDF icon 13-review-of-whistleblowing-policy.pdf74.31 KB
For decision
14 Performance Monitoring
14a Public Value Performance Measures 2011/12

This report, attached marked 14a, presents a summary of the Service's performance for the period April to December 2011, as recorded against the Public Value performance measures set out in the 2011/12 Service Plan.

AttachmentSize
PDF icon 14a-public-value-performance-measures-2011-12.pdf98.12 KB
For decision
14b Retained Duty System Performance Monitoring October to December 2011

This report, attached marked 14b, provides information regarding the ongoing performance of the Retained Duty System in Shropshire.

AttachmentSize
PDF icon 14-rds-performance-monitoring-oct-to-dec-2011.pdf177.74 KB
For information