Audit and Performance Management Committee

Members are asked to receive the minutes of the Audit and Performance Management Committee meeting, held on 1 March 2012, attached marked 5, and consider the recommendations at items 8, 12 and 13.

Item 8 – Internal Audit Programme 2012/13 to 2015/16
A copy of the report, containing the recommendations to be considered is attached marked 5a.

Members are also asked to note the decision made by the Chief Fire Officer to purchase internal audit services from Shropshire Council following consultation with the Treasurer, Monitoring Officer and Chair of the Fire Authority. The decision was made on the basis set out in section 3 (page 2) of paper 5a. Under section G5 of Standing Orders relating to Contracts (the relevant subsections of which are set out below), such decisions must be reported to the Authority.

G When tenders are not required

G5 A contract may be entered into by the Authority other than in accordance with Standing Order F in the following circumstances, subject to consultation with the Chair and Treasurer of the Authority:

(ii) where it has been decided to standardise by buying from only one supplier.

(iii) for the extension of, addition to, or maintenance of, existing goods, materials or services, where this can only be done satisfactorily by the original contractor or supplier.

(vii) where the Chief Fire Officer enters into a contract as described in sub-clauses (i) to (vi) above, it must be determined that such action is reasonable and a written record must be entered in the Register of the action taken and the reason and reported to the Authority.

Item 12 - Anti-Fraud and Corruption Strategy
A copy of the Strategy to be considered is attached, marked 5b.

Item 13 – Whistleblowing Policy
A copy of the Policy to be considered is attached, marked 5c.

Parent meeting: 

25 April 2012

Status: 

For decision

Item no.: 

05

Attachment: 

Legacy: